Project Owner
City of Eloy
Location
Eloy, AZ
Project Overview
The assessment work included civil, mechanical, structural and electrical/instrumentation inspections of the lift station followed by a summary memorandum by discipline. In addition to condition assessment, Valentine evaluated wet well capacity and pumping requirements for build-out conditions based on build-out requirements. This analysis considered structural, E&IC, civil and process mechanical impacts as well as construction and operations costs. Valentine prepared conceptual drawings to assist with cost development and alternative evaluation. A final report summarized the results and recommendations for the lift station assessment as well as a prioritization of the rehabilitation efforts.
Key Project Features
Complete System Assessment
Rehabilitation Prioritization
Capacity Evaluation & Master Planning
Copyright Valentine Environmental Engineers, LLC Sept 2021